经过近3个月的紧张施工,引黄入卫一期工程顺利完成,位山引黄闸于1月30日10时开闸放水,过闸流量50m~3/s。这次送水时间计划一个月,送水5000万m~3,将使河北省东南部地区缺水严重状况得以缓解。 引黄入卫工程是国家确定的跨省、跨流域的大型调水工程。它从山东位山引黄闸引水,途经东阿、阳谷、聊城、冠县、临清等县(市)入卫运河,引水渠道全长104km。该工程于1992年11月5日开工,计划三年完成,届时每年可
After nearly three months of intense construction, the first phase of the Yellow River Diversion Project was completed successfully. The Yellow River Diversion Project opened its gate at 10 am on January 30 and opened the gate. The overrun flow was 50 m 3 / s. The water supply plan for a month, water 50 million m ~ 3, will make the severe shortage of water in southeast of Hebei Province to be alleviated. The Yellow River Diversion Project is a large-scale water diversion project that is determined by the state to be trans-provincial and inter-basin. It leads the Yellow River gate from Shandong Bit Hill and passes through Dong’A, Yanggu, Liaocheng, Guanxian and Linqing counties (cities) into the canal, and the diversion channel covers a total length of 104km. The project started on November 5, 1992, is scheduled to be completed in three years, then every year