云锡老厂背阴山冲尾矿库于1977年8月已经超过原定标高运行,直接威胁老厂锡矿选厂一工段、胜利坑口的工业设施及居民区的安全。为了保障下游生命财产的安全,老厂选厂二工段被迫停产。当时如若重新觅建尾矿库来解决该厂的尾矿堆放,需要2~3年的建设时间,生产损失太大。所以,决定对背阴山冲尾矿库进行加固、挖潜,扩大库容。
The Yinchu old factory shady mountain red tailing pond in August 1977 has been more than the original scheduled run high, directly threaten the old factory tin processing plant a section, the industrial pit of Hang Hau and the safety of residential areas. In order to protect the safety of life and property downstream, the second factory section of the old factory was forced to stop production. At that time, if re-establish the tailings pond to solve the tailings dumping of the plant, it takes 2 to 3 years of construction time, production loss is too large. Therefore, we decided to reinforce the Chong Yin Shan red tailings reservoir, tapping potential and expanding storage capacity.