日前湖南省最大的液化石油气混空气城市燃气工程在衡阳市正式建成投产,衡阳从此结束了无城市管道燃气的历史。衡阳市燃气工程的通气,不仅牵动着中央、省、市领导的心,而且实现了雁城居民期盼已久的夙愿。煤气工程原计划于1995年底投产供气,由于前期非生产性设施投入过多,管理失控,使得主要依靠社会集资和出售煤气债券等的资金来源严重不足,形成巨大的资金缺口,造成工期一拖再拖,工程被迫于1997年元月停工,并
Recently, Hunan Province, the largest liquefied petroleum gas mixed air city gas project was officially put into operation in Hengyang City, Hengyang has ended without the history of urban gas pipeline. The ventilation of Hengyang Gas Project not only affects the leaders of the central, provincial and municipal governments, but also realizes the long-awaited wish of the residents in Yancheng. Gas projects were originally planned to be put into operation by the end of 1995. As a result of excessive investment in non-productive facilities in the early stage and out-of-control management, the sources of funds mainly relying on social fund-raising and the sale of gas bonds were seriously insufficient and a huge funding gap was formed, resulting in a delay in construction Further delay, the works were forced to stop working in January 1997 and