北安电厂五期扩建工程,由原黑河地区第二建筑工程公司承担土建施工任务。主厂房为予制排架结构,跨度为25m+18m,柱高21m。全柱重近38t。因当时起重设备小,柱子不能整体起吊,所以将柱子分节予制。按施工组织设计要求,柱子要在一九七六年十月十五日予制完,但因缺少钢材,未能按计划完成予制任务。十二月初钢材突然进场,为确保七七年三月一日开吊。但当时土
The second phase of Bei’an Power Plant expansion project was undertaken by the former Heihe Area Second Construction Engineering Company for civil construction tasks. The main factory building is prefabricated with a span of 25m+18m and a column height of 21m. The whole column is nearly 38t. Since the lifting equipment was small at that time, the column could not be lifted as a whole, so the column was divided into sections. According to the requirements of the construction organization design, the pillars must be finished on October 15, 1976. However, due to the lack of steel, they failed to complete the preparatory tasks as planned. In early December, steel suddenly entered the yard to ensure that it was opened on March 1st, 2007. But at the time