西德鲁尔煤炭公司瓦尔朱姆煤矿维尔德立井,井深1060米,净径6米,井筒穿过第四纪和第三纪地层的厚度约为300米,而在深度600米范围以内均为含水不稳定地层,故确定采用冻结法施工,冻结孔深度为581米。维尔德井已于1981年4月开始掘凿,目前(1981,6.12)已掘凿了76米。由于该井施工具有一定的困难,但其又将为今后的深井冻结工程提供经验,故该工程项目得到联邦政府的资助。为此在设计、科研和现场施工人员密切合作下,进行了下述重点研究项目,即:冻结壁—外井壁共同承载系统的选择;新的冻结工艺;对冻结壁状况进行长时监测;冻结井段的掘凿和外井壁的砌筑方法;冻结
The Wellder Coal Company in West Druid Weierdeli mine wells, 1060 meters deep and 6 meters in net diameter, the borehole through the Quaternary and Tertiary stratigraphic thickness of about 300 meters, and within the depth of 600 meters are Water instability formation, it is determined to freeze construction, freezing hole depth of 581 meters. The Wilde well began digging in April 1981 and has now been dug 76 meters (1981,6.12). Due to some difficulties in the construction of the well, it will provide experience for the future deep well freezing project. Therefore, the project is funded by the federal government. To this end in the design, research and field construction personnel in close cooperation, carried out the following key research projects, namely: frozen wall - outer wall co-bearing system selection; new freezing process; frozen wall condition for long-term monitoring; Freezing section digging and outer wall masonry method; freezing