水利工程施工进度安排,历史上多沿用横道图法。这种方法的优点是方便、直观、易懂,但不能反映工序之间的逻辑关系和相互依赖关系,施工人员不易抓住重点,容易造成窝工浪费,引起经济损失。国外在六十年代就盛行用网络计划新技术编制施工进度和资源计划。我国已故著名数学家华罗庚教授也早已提倡引用这种新技术。目前我国在科研、生产、水利等部门已逐步推广使用,并已取得效果。为了使这种新技术能在我省水利工程施工管理中推广应用,现以××市第二热电厂江边水泵站工程为例,利用网络法原理对工程的工期和费用的优化问题(资源优化从略),做点粗浅尝试,望能起到抛砖引玉的作用。
Water conservancy construction schedule, the history of the use of horizontal road map. The advantage of this method is that it is convenient, intuitive and easy to understand. However, it can not reflect the logical relationship and interdependence between processes. It is not easy for constructors to grasp the key points, which can easily lead to waste of labor and economic losses. Overseas in the sixties on the prevalence of network planning new technology construction schedule and resource planning. Professor Hua Luogeng, the late famous mathematician in our country, has long advocated quoting this new technology. At present, China has gradually promoted the use of scientific research, production, water conservancy and other departments and has achieved results. In order to make this new technology popularize and apply in construction management of water conservancy projects in our province, taking the waterfront pumping station project of No.2 Hydropower Plant in ×× City as an example, this paper uses the principle of network method to optimize the project schedule and cost optimization Omitted), do something superficial try, hope can play a valuable role.