近日,“华龙一号”全球首堆示范工程福清核电5号机组环吊480吨安装小车载荷试验完成,环吊安装小车和运行小车全部可用,比计划提前18天完成(图(1))。截至10月21日,福清核电5号机组龙门吊载荷试验全部完成,这标志着主设备运输通道全部打通,为首台蒸发器及后续主设备的安装创造了必要的条件(图(2))。与此同时,“华龙一号”国内首台ZH-65型蒸汽发生器从位于广州南沙的东方电气
Recently, the load test of the 480-ton hoisting crane for the No.4 hull of Fuqing NPP was completed. The hoisting crane and the running hoist were all available, which was completed 18 days earlier than planned (Figure 1) ). As of October 21, Fuqing Nuclear Power Unit 5 gantry crane load test was completed, which marks the opening of the main equipment transport access, for the first evaporator and follow-up installation of the main equipment to create the necessary conditions (Figure (2)). At the same time, “Hualong One” China’s first ZH-65 steam generator from the Guangzhou Nansha Dongfang Electric