承包商在合同工期对己方严重不利、仓促开工、业主态度强硬的局面下,通过理性博弈,缓解了巨大的工期压力,解除了巨额工期罚款的风险。苏丹罗塞雷斯大坝加高工程(以下简称“本项目”),位于非洲青尼罗河干流上。原大坝于20世纪60年代末建成,高66米,长13.5公里,包括长1公里的混凝土坝及长12.5公里的左右岸土石坝。电站装机7台,共28万千瓦。本项目是在原有大坝基础上加高10米,加高后大坝全长25.1公里,将储存更多青尼罗河上游来水,为下游广大灌溉区域提供更加可靠稳定的供水,水库总库容将从34亿m3增加到74亿m3;同时,大坝加高后,不仅可以提高该水电站
Under the situation that the contract duration is seriously unfavorable to one’s own, the construction is started harshly and the owner’s attitude is tough, the contractor alleviates the huge construction period pressure and lifts the risk of a huge amount of construction period penalty through a rational game. Sudan Luosresi dam heightening project (hereinafter referred to as “the project ”), located in Africa, the main blue-green Nile. The dam was completed in the late 1960s at a height of 66 meters and a length of 13.5 kilometers, including a concrete dam of 1 km in length and an earth-rock dam of about 12.5 km in length. Power station installed 7 units, a total of 280,000 kilowatts. This project is to increase the height of 10 meters on the basis of the original dam. After the elevation is completed, the total length of the dam will be 25.1 kilometers. More dam water will be stored in the upper reaches of the Blue Nile. This will provide a more reliable and stable water supply for the downstream irrigation areas. From 3.4 billion m3 to 7.4 billion m3; the same time, the dam increased, not only can increase the hydropower station