第一設計院設計的“吊軌梁及开挖支撑”的西北地区通用图(图号原为壹桥0146,1964年8月修改为壹桥0159),自应用以来,已有二年多的时間。对于施工部門来說,这份图用处很大。特别是在支援农业的工点,在既有綫上設置小桥涵,即可在不封閉綫路的情况下进行施工。实践証明,这种施工方法是比较好的方法。在一年多的应用过程中,我們曾发現有盲目搬用这个通用图的现象。以致在高路堤、松軟地基、沼泽地带施工时,未經結合地质情况,詳細检算有无基底凸出可能,即指定使用这份通用图。这是不够妥当的。为此,
The first design institute of the “hanging rail beams and excavation support,” the Northwest General map (Figure No. One former bridge 0146, August 1964 changed to One Bridge 0159), since the application has been more than two years time. For the construction department, this figure is very useful. In particular, at construction sites that support agriculture, small bridges and culverts can be installed on existing lines to carry out construction without closing the line. Practice has proved that this method of construction is a better way. In the course of more than a year of application, we have found that there is a phenomenon of blindly moving this generic graph. So that in high embankments, soft ground, marsh zone construction, without the integration of geological conditions, a detailed examination of whether the substrate protruding may specify the use of this common map. This is not proper enough. to this end,