我矿国各庄采区是一座较大规模的粘土矿井。为了加快它的副井开拓延深工程,在矿党委领导下,我们组织了工人、干部、技术人员三结合研究组,通过认真调查和方案比较,先后由-65米水平至-155米水平和-155米水平至-255米水平两个阶段采用了吊罐反井施工方法。实践证明,这种施工方法与一般方法相比,速度快、效率高、比较安全;取得了较好的技术经济指标。
Mine mining Zhuang mining area is a larger clay mine. In order to speed up its auxiliary wells to develop and deepen the project, under the leadership of the coal mine party committee, we organized three combined research groups of workers, cadres and technicians. Through careful investigation and comparison of plans, the project has successively expanded from -65 meters to -155 meters and -155 m level to -255 m level The two stages of the anti-shaft crane construction method. Practice has proved that this construction method compared with the general method, fast, high efficiency, more secure; achieved good technical and economic indicators.