本文叙述马格马铜公司新建奥托昆普闪速炉的开炉与操作情况。这台闪速炉采用奥托昆普的最新技术,设计能力为907000t/a铜精矿。闪速炉及其辅助设备于1986年10月开始建造。1988年6月和7月初进行试运转。以创纪录的速度建造的这座闪速炉,是第一次将现有的冶炼厂改建成奥托昆普式的冶炼厂。在投产的头5个月内,闪速炉的在线时间平均达80.75%。由于存在一系列问题(包括精矿从干矿仓到刮板运输机呈“流态化”;废热锅炉长炉结;精矿喷嘴的工作性能不好,特别是进料量低时),妨碍了在连续作业时期内将闪速炉的处理能力提高到设计水平。最近,对有关设备进行了改造,加上冶炼厂全体员工的共同努力,使炉子的工作效率和性能得到了改善。
This article describes the furnace and operation of the new Outokumpu flash furnace at Magmar Copper. This flash furnace uses Outokumpu’s latest technology and has a design capacity of 907,000 t / a copper concentrate. The flash furnace and its ancillary equipment began construction in October 1986. June 1988 and early July trial run. The flash furnace, built at a record pace, was the first to convert an existing smelter into an Outokumpu smelter. In the first 5 months of operation, flash furnaces averaged 80.75% of the online time. As a result of a series of problems (including the “fluidization” of concentrates from dry mills to scraper conveyors; long furnace junctions for waste heat boilers; poor performance of concentrate nozzles, especially at low feed rates) In the continuous operation of the flash furnace during the handling capacity up to the design level. The recent revamping of the equipment, coupled with the joint efforts of all staff in the smelter, has led to improvements in furnace efficiency and performance.