案例2005年5月10日,发包人甲公司与承包人乙公司签订建设工程施工合同一份,合同约定:由乙公司承建某综合楼工程,工程款支付采取分阶段支付的方式。合同签订后,乙公司依照合同约定时间如期开工。该综合楼地下室工程完工后,因甲公司未及时支付工程款.乙公司无法施工,因此,乙方不得不停止施工并依合同约定向甲方发出停工通知。此后,甲公司未再支付任何工程款,经乙公司
Case On May 10, 2005, the employer A contracted with the contractor Company B to sign a construction contract. The contract stipulated that the company B should undertake the construction of a general building project and pay the construction funds in stages. After the signing of the contract, Company B started the work as scheduled on time. After the completion of the complex basement project, Company A failed to pay the construction cost due to the failure of Company B. Construction Company B was forced to stop construction and issue a stop notice to Party A according to the contract. Since then, a company no longer pay any construction funds, the company B.