(一)计划概要甲、总则:为了保证一九五二年完成导沭工程,按照原计划施工程序,本期的土、石工需要调集民工一四五,五三二人,料石工一○○○人,实做工作时间为两个月,并决定十月初部份开工,十五号全部开工。乙、工程主要项目:1、继续开挖引河石方八○万公方。2、续挖引河土方二三○万公方,将引河下段的土方,大体挖完。3、作成沙河上中游筑堤及裁弯切角土方的百分之六十,计五一○万公方。4、开挖引河上口主要建筑物(溢水揠及穿沭涵洞)基槽并采运条
(I) Outline of the Project A. General Provisions: In order to ensure the completion of the Linshu Project in 1952, according to the original planned construction procedures, the current earthwork and masonry need to be transferred to 145 or 532 migrant workers, ○ people, actually working hours for two months, and decided to start some in early October, all started on the 15th. B, the project main projects: 1, continue to excavation lead river stone 80,000 square. 2, continued excavation of 20 million square river side of the earth, will lead the river under the earth, generally finished digging. 3, making the upper reaches of the Shahe embankment and cut corner cut earth 60%, accounting for 510,000 square. 4, the excavation of the river leading to the main buildings (overflow 揠 and Shu-culvert hole) and the tank base transport