辽宁省宽甸县夹皮沟乡河圈电站实行分项招标建站,取得了提前一年工期,节约资金23.36万元的显著效果。乡政府在确定标底时,对14家投标单位,宣布了三项原则:①不能突破预算;②要坚决保证二期:③对投标承建单位进行认真、彻底的现有设备、已建工程质量的严格考察。然后,分别把拦河坝、输水洞、厂房承包给三个不同的施工单位。承包后,工地建立了指挥部,对三个承包单位进行统一指挥,对工程进度统筹安排,对工程质量实行统一检查,验收。同时,乡政府还与县物资供应总公司和施工承包单位签订了物资供应合同,避免了在物资供应上的扯皮现象,没因材料的供应而影响了施工进度。
The Hekou Power Station in Jiapigou Township, Kuandian County, Liaoning Province, implemented a sub-item bidding to build a station, which achieved a one-year construction period in advance and saved the capital of 236,600 yuan. When the township government fixed the bid, it announced three principles to 14 bidders: 1 It was impossible to break through the budget; 2 It was necessary to guarantee the second phase: 3 Serious and thorough existing equipment and construction quality of the bidding contractor Strict inspection. Then, the barrage, water tunnel, and workshop were contracted to three different construction units. After contracting, a command post was set up on the construction site to conduct unified command for the three contracting units, to make overall arrangements for the progress of the project, and to implement unified inspection and acceptance of the project quality. At the same time, the township government also signed a material supply contract with the county’s material supply company and the construction contractor, which avoided the wrangling on the supply of materials and did not affect the construction progress due to the supply of materials.