我处承担贾汪电厂6,000瓩机35吨/小时炉的安装与土建任务,从9月13日设备到达现场起,以18天的时间、在9月30日送汽、发电,光荣地完成了党交给我们的任务。这是采取以下措施取得的巨大成果。扫清畏难情绪,把任务交给羣众我处所担负的韩庄、贾汪两个工程,从8月份工作进度来看,韩庄工程较快,且材料、设备到货也较多,在客观上较贾汪容易一些。但韩庄地区输电线路跟不上。因此上级要求先突击完成贾汪工程,要求在国庆节前供应煤矿电力。由于贾汪工期紧,设备缺少很多,工地的搬运、起重、焊接等机具没有,技术力量薄弱,准备
I assume Jiawang Power Plant 6,000 瓩 35 tons / hour furnace installation and civil construction tasks, from September 13 equipment arrived on the scene, with 18 days, on September 30 to send steam, power generation, honored to complete The task given to us by the party. This is a tremendous achievement achieved through the following measures. Clear the fear of the situation, the task entrusted to the masses I place Hanzhuang, Jia Wang two projects, from the progress of work in August point of view, Hanzhuang project faster, and more materials and equipment arrival, objective Jia Wang easier than some. But Hanzhuang area transmission line can not keep up. Therefore, the superior asked first to finish the project of Jiawang and request the supply of coal mine power before National Day. As Jia Wang tight schedule, the lack of a lot of equipment, site handling, lifting, welding and other equipment does not have the technical strength of weak, ready