论文部分内容阅读
前言茂名热电厂的№3、4炉为武锅WGZ410/100—3型微正压燃油锅炉,于1975年初和年底相继投产。为察明燃烧性能、确定运行方式及技术经济参数,以及探索烟气的酸露点及低温腐蚀特性,于1977年6月在电厂的组织领导下对两台炉进行了燃烧调整试验;参加单位有武汉锅炉厂、广东中试所、江苏中试所、浙江大学及水电部热工所。
Preface Maoming Thermal Power Plant № 3,4 furnace for the wok WGZ410 / 100-3 type of micro-pressure oil-fired boiler, in early 1975 and the end of the year have been put into operation. In order to ascertain the combustion performance, to determine the operation mode and technical and economic parameters, and to explore the flue gas acid dew point and low temperature corrosion characteristics, in June 1977 under the leadership of the power plant on the two furnaces combustion adjustment test; Participating units have Wuhan Boiler Factory, Guangdong Pilot Institute, Jiangsu Pilot Institute, Zhejiang University and the Ministry of Thermal Power.