经过3年紧张施工,上海市“十一五”重大工程,耗资170亿元的青草沙原水系统基本建成,除南汇支线主体工程力争在2010年底开工并在2012年1月通水以外,其他均已具备调试通水条件。通水切换2010年12月1日启动,分4批进行,计划至2011年6月中旬全面完成,涉及杨树浦、长桥、南市水厂和浦东的临江、陆家嘴、居家桥、金海、凌桥水厂等8座水厂。切换水量为560万m~3/d。通水切换计划分4
After three years of intensive construction, the “11th Five-Year” major project in Shanghai was basically completed with a total cost of 17 billion yuan. Apart from the main project of Nanhui Branch striving to start construction by the end of 2010 and open water in January 2012, Other have been equipped with debugging water conditions. The water switch will be launched on December 1, 2010 in four batches. The plan will be fully completed in mid-June 2011 and will involve Linjiang, Lujiazui, Juqiao, Gimhae and Ling in Yangshupu, Changqiao, Nanshi Waterworks and Pudong Bridge Water Works and other eight water plants. Switching water is 5.6 million m 3 / d. Water switching plan points 4