乐清湾1号桥采用的是“短线法”预制节段拼装工艺,精度要求高,测量难度大。经与同行业咨询后,未发现有特别的节段梁测设方法,多数还是采用基本放样手段,通过控制“轴线”然后靠工人的操作熟练度来完成测设,随机性太大。通过研究和理论误差分析,发现控制墩顶块的“平面旋转”才是控制拼装线形的关键点,并借此创新测设工艺、精确控制其空间姿态、加强梁体的变形观测,实现了墩顶块的精确定位。工后检测显示,各项精度指标均符合要求。
Yueqing Bay Bridge No. 1 is used “short-term method ” prefabricated segment assembly process, high precision, difficult to measure. After consulting with the same industry, we did not find a special method for measuring and setting section beams. Most of them still use basic lofting methods to complete the surveying and mapping by controlling the “axis” and then by the proficiency of workers. The randomness is too large. Through the research and theoretical error analysis, it is found that the “plane rotation” of the top block of the control pier is the key point for controlling the assembly line shape, and by this means, the new measuring and setting technology can be used to precisely control the spatial attitude and strengthen the deformation observation of the beam. The precise positioning of the pier block. After-sales testing showed that the accuracy of the indicators are in line with the requirements.