截止5月17日,2000年黄河下游第一期防洪工程建设安排山东河务局的105项建设项目,已有75项竣工或完成计划任务,全局累计完成土方2189万m~3、石方24.2万m~3、混凝土1.67万m~3,分别占计划的90%、100 %和76%。2000年第二期防洪工程建设安排山东河务局的101项建设项目,已开工86项,有25项已竣工或已完成本期计划任务,累计完成土方
As of May 17, 2000, the first phase of the construction of the flood control project in the lower reaches of the Yellow River arranged for 105 construction projects in Shandong Bureau of Water Resources, 75 of which were completed or completed the planned tasks. The cumulative total of 21.89 million m 3 earthwork, 24.2 stonework Million m 3, and concrete 16,700 m 3, accounting for 90%, 100% and 76% of the planned respectively. The second phase of flood control project construction in 2000 101 sets of Shandong River Construction Project, has started 86, 25 have been completed or have completed the current planning tasks, the cumulative completion of the earth