在白灰焙烧结构工程中,我们二队二工段主要是负责结构件安装工作的。在公司领导指示和具体业务部门帮助下,从一九六五年九月开始试行统筹方法,至今不到五个月。试行过程中效果较好,如原料间厂房工期,计划36天,实际工期提前了四天,竖窑安装计划41天,实际21天就达到了砌砖条件。(一)没有实行统筹方法以前,我们工段安排和组织施
In the lime-ash roasting structure engineering, the second section of the second team is mainly responsible for the installation of structural parts. With the help of the company’s leadership instructions and the help of specific business units, the piloting of the method of co-ordination began in September 1965 and it has been less than five months. In the trial process, the results were good. For example, the duration of the workshop for the raw materials was 36 days. The actual construction period was four days earlier. The shaft kiln installation plan was 41 days, and the actual 21-day bricklaying conditions were achieved. (I) Before the implementation of the overall method, we arranged and organized the works