1 项目概况为扩大粮食储备能力,完善粮库中转发放功能,提高现有一、二期设备的利用率,新沙港直属粮库三期工程于2002年3月开工建设。主要包括:3×5排列浅圆仓,总仓容10万吨;4座简易工作塔;打包站;火车发放塔;输送栈桥;变配电室以及其他设施。在三期工程中,运达伟业公司分包项目包括: ●设备采购(含计算机、PLC设备、控制箱柜、电缆、传感器等)
1 Project Overview In order to expand the capacity of grain reserves, improve the function of grain storage and transshipment, and improve the utilization rate of the existing first and second phase equipment, the third phase of the new grain depot in Xinsha was started construction in March 2002. Including: 3 × 5 arranged shallow round warehouse, the total storage capacity of 100000 tons; 4 simple work tower; packing station; train delivery tower; delivery trestle; change the power distribution room and other facilities. In the third phase of the project, Wan Dawei company subcontracting projects include: ● equipment procurement (including computers, PLC equipment, control cabinets, cables, sensors, etc.)