原计划第三金铜矿在五一年度,本坑每月必需生产6000~7000吨矿石,即每天平约需要生产200~240吨矿石,因此该坑竖井罐笼每班时平约要提到70~80吨,而又由於该竖井在五一年仍要不停的下掘,再加土该坑之内白探矿掘进的废石,也要从此竖井出来,致该竖井罐笼的卷扬能力,必须全班时达到一百余吨。但是在五○年内,该竖井罐笼翻扬能力,三个班时合计假能運出150吨左右,则两者相差甚为
The original planned third gold and copper mine in the year 51, the pit must produce 6,000 to 7,000 tons of ore per day, that is, daily production of about 200 to 240 tons of ore, so the pit shaft cage every class to mention about 70 ~ 80 tons, but also because of the shaft in 51 year still keep digging, coupled with the pit of white earth exploration excavation waste rock, but also from the shaft out to the shaft of the hoisting capacity of the cage, Must be a whole class to reach more than 100 tons. However, in 50 years, the vertical cage cage capacity, three class total false can be shipped out of about 150 tons, the difference between the two is very