在中洛输油管道建设中由于施工原因,致使泵站出口 8 km处的管段在投产预热中严重变形(见图1、图2),局部阻力增大,限制了泵站出口的输油压力,成了全线“卡脖子”段,造成中洛线长期达不到设计输油能力。 鉴于冷冻封堵技术室内试验已经成功,在管道局倡导下,由新乡输油公司与大连光明化工研究所合作,在中洛线变形管段换管中应用了这一新技术。光明所负责管道冷冻封堵与解冻,新乡输油公司负责技管施工。并确定在实际应用之前,光明所完成管材的低温性能试验,两家共同开展现场模拟试验和编制冷冻封堵换管施工组织设计。
Due to the construction reasons in the construction of Zhongluo Oil Pipeline, the pipe segment at 8 km at the outlet of the pump station was seriously deformed during the preheating (see Fig. 1 and Fig. 2). As the local resistance increased, the oil pressure at the exit of the pump station was limited , Has become the “card neck” section, resulting in long-term non-line design oil capacity. In view of the freezing chamber technology has been successfully tested in the laboratory, initiated by the pipeline bureau, Xinxiang Oil Company and the Dalian Institute of Chemical Guangming cooperation in Zhongluo deformation tube section of the tube in the application of this new technology. Light is responsible for freezing and thawing of pipes, Xinxiang Oil Company is responsible for technical construction. And to determine before the actual application, the light of the pipe to complete the low temperature performance test, the two carried out on-site simulation test and the preparation of the construction of frozen block pipe design.