南水北调中线鹤壁段渠道在地基处理过程中发现多条洞穴,深度在地面线下3~15m不等,洞径一般1.5~2m,最大处达4~5m,长度可达百余米,经勘查为当地村民为建房掏沙所致。人工掏沙洞在遇水或上部荷载加大情况下,易造成塌方、沉陷等破坏,危害总干渠运行安全。根据人工掏砂洞的埋深和与渠底板的关系分别采用不同的处理方案:对人工掏砂洞埋藏较深位于渠底板以下一定深度内的渠段采用灌浆处理措施;对人工掏砂洞埋藏较浅,位于渠底板以上或渠底板附近的渠段,采用直接挖除换填处理措施。该处理方案目前已完成,总干渠已安全通水。
Hebi section of the central route of South-to-North Water Diversion Project found a number of caves during foundation treatment. The depth of the caves varied from 3 to 15 m under the ground line, with a typical bore diameter of 1.5 to 2 m and a maximum of 4 to 5 m and a length of up to 100 m. Local villagers dig for sand due to building. Artificial digging sand hole in the case of water or the upper load increases, easily lead to landslides, subsidence and other damage, endanger the operation of the main canal security. According to the depth of the artificial sand hole and the relationship with the drainage base plate, different treatment schemes were adopted respectively: grouting treatment was applied to the canal buried deep in the artificial sand tunnel below a certain depth; Shallow, located in the canal above the floor or near the canal section of the canal, using direct digging replacement measures. The treatment plan has now been completed and the main canal has been safe and water-filled.