论文部分内容阅读
吊车梁的升级改造加固设计邱洪兴,曹双寅,朱中益(东南大学土木工程学院210096)(锡山市建筑工程质量监督站214011)1.工程概况锡山市某单层厂房,柱距为6m,跨度为24m,厂房长96m。原设计2台30t中级工作制吊车,采用G323(二)图集中的...
The upgrade, reinforcement and design of crane girders Qiu Hongxing, Cao Shuangqi, Zhu Zhongyi (School of Civil Engineering, Southeast University, 210096) (Qishan City Construction Engineering Quality Supervision Station, 214011) 1. Project Overview Xishan City, a single-storey plant, column spacing of 6m, span of 24m, plant length 96m. The original design of 2 sets of 30t intermediate working cranes, using the G323 (two) map...