临沂市国家安全局办公楼整体平移工程技术复杂、施工难度大 ,在平移施工中加强了质量控制和现场监测工作。在此 ,介绍了上下轨道施工、柱子切断及托换施工、牵引力控制及监测、顶升换向及导向装置 ,并给出了沉降观测结果
The overall translation project of the office building of Linyi City State Security Administration is complicated and the construction is difficult. The quality control and on-site monitoring are strengthened during the construction of the translator. Here, the construction of the upper and lower railways, the construction of the columns and the undercarriage, the control and monitoring of tractive force, the lifting and reversing and guiding devices are introduced, and the settlement observation results are given