我们于1984年冬季在中国银行金融大楼的外饰面工程中进行了花岗石薄板湿法施工,施工质量良好。一、工程概况本工程位于北京阜成门外西二环立交桥东南角(处于西北风口地段),为内筒外框结构,总高81.10m,建筑面积27285m~2。外墙从-0.90m至12m为湿法施工(花岗石薄板镶贴),1038m~2墙面及柱面于1984年12月20日开始,利用冬季75天时间做完。
In the winter of 1984, we carried out wet construction of granite thin slabs in the exterior cladding project of the Bank of China Financial Building. The construction quality was good. I. Project Overview The project is located at the southeast corner of the Xi’erhuan overpass in Fuchengmenwai, Beijing (at the northwestern outlet section). It is an inner-tube outer frame structure with a total height of 81.10m and a building area of 27285m~2. The external wall is constructed from wet construction (between -0.90m to 12m) (inlaid with granite sheet), and the wall surface and column surface of 1038m~2 began on December 20th, 1984, and was completed in 75 days in winter.