摘要:10kV配电室是由配电变压器、高压开关柜、低压开关柜、母线及其辅助设备,按一定的接线方式组合排列而成的电力设施,其作用是变换电压和分配电能并直接就近向低压用户供电,它是城市供配电系统中的重要组成部分。配电室的安装施工工序比较复杂,电气设备安装质量要求较高。文章分析了1O kV 配电室安装时施工过程中几个重要环节,并提出安装施工过程中应注意的问题及应对措施,以保证工程质量。
关键词:配电室;安装施工;控制措施
Abstract:10kV distribution chamber is composed of distribution transformer, high voltage switchgear, low voltage switch cabinet, busbar and its auxiliary equipment, according to a certain mode of connection is combined and arranged into power facility, its role is to transform and distribution of electric voltage and direct the nearest to the low-voltage power supply, it is the city of supply and distribution system in of the importance constitute part. Power distribution room to install the construction process is relatively complex, high quality requirements of electrical equipment installation. The article analyzes the 1O kV distribution room installation construction process on several important aspects, and puts forward the construction process should pay attention to the problems and corresponding measures, in order to ensure engineering quality.
Key words:Electricity distribution room;Installation and construction;Control measures
中图分类号:TM641 文献标识码:A文章编号:2095-2104(2012)
前言:
随着广东地区全面建设小康社会步伐的加快和城市化建设的快速发展,中小城镇居民住宅小区的建设如雨后春笋般的发展起来,中小城镇居民小区的出现,说明了改革开放以来,人们生活得到了极大改善,同时,也为电力企业实现可持续发展,营造了一个大好的发展机遇。
1 安装施工过程及要求
10 kV配电室安装施工主要包括土建施工、基础型钢的施工、高低压开关柜的安装、桥架和母线支架施工、母线安装以及电缆进出线的施工。以下表一详细分析安装施工过程的具体要求。
2 施工过程中的控制措施
通过以上分析可以看出,配电室内部施工工序较多,内部因素彼此之间也形成了互相制约的条件。为确保配电室工程质量,首先应建立配电室安装施工中的管理措施,对设备安装中各工序严格按照GB 50303—2002《建筑电气工程施工质量验收规范》的要求进行施工。配电室的安装施工质量控制分为准备、施工、调试和送电4个关键环节,在各个环节建立有效的管理措施,并严格执行,按照质量标准检查、监督。
2.1 准备环节控制措施
供电部门对配电室一次原理图进行审核并确认,设计部门对设备中标厂家提供的高低压配电系统二次原理图审核确认。电气设备到场后,监理部门验收资料是否齐全,设备资料和厂家提供的配件及钥匙等设专人管理,防止重要资料及钥匙丢失。
设备安装前编写施工组织设计和设备施工方案,审批后方可进行设备安装施工。施工中严格按照图纸及厂家提供的基础图进行基础、接地装置及管线的预留预埋。预留预埋时,电气施工人员要与土建施工密切配合,确保槽钢基础的水平度、平行度
符合规范要求。槽钢基础施工完毕后要使用水准仪进行实测验收,当水平度和平行度不满足规范要求時,要进一步进行调整,直至符合规范要求为止。
2.2 施工环节控制措施
安装施工阶段主要包括高低压开关柜的就位、高低压开关柜内铜排穿引安装及二次线的穿引敷设、高低压桥架的安装、母线的安装、风管的安装,设备安装中各工序要严格按照标准要求进行施工。对于常见的设备质量问题(如零排缺件、母排的固定支架数量不够、开关的复位按钮不能复位、个别元器件缺失、设备外壳接地线线径过小或未直接与接地体连接等)应逐一排查、验收,整改不符合要求项。
设备安装阶段工序按先后依次为:高低压设备的就位,高低压开关柜铜排穿引及二次线的敷设,封闭母线的安装、风管的安装、桥架的安装。这样安排可尽可能减少各工序之间的破坏及污染,保证施工进度。就位安装按照从里到外的顺序依次进行,以便于后续设备的运输和安装。质量控制措施主要从以下几个方面进行控制:做好配电室桥架、母线、风管、设备的综合平面图,确定好位置、标高。如果它
们之间的标高或者位置出现矛盾,原则上应优先考虑设备的位置和标高,再考虑母线的位置和标高,然后是风管的位置和标高,最后是桥架的位置和标高。
2.3 调试环节控制措施
设备调试及送电方案编制审批完毕,设备调试所需要的仪器准备齐全,配电室电气设备试验全部合格,如变压器、断路器、电缆的耐压试验;变压器各绕组的直流电阻值、变比试验;断路器失压脱扣和重合闸试验;直流屏的试验;计量TA 和TV 的试验;低压电器设备的试验,低压开关柜与低压开关柜之间联络用低压断路器接三相电模拟试验等。
2.4 送电环节控制措施
送电前应对下列工作内容进行逐条落实:计量表的安装;进线保护的整定;各种合同协议的签订;运行规程的编制;运行人员的取证、培训;配电室内安全用具的配备(如绝缘板、灭火器、绝缘手套、绝缘鞋、验电器、标志牌、规章制度牌、接地线、应急灯等);直流屏的充电,便于高低压开关柜的操作;悬挂高低压二次接线图等。
送电时,送电顺序必须严格按照送电方案执行,操作过程必须符合规范要求。操作人员必须持证上岗并充分了解配电室内的一二次配电原理。
3 结束语
10 kV配电室是电能控制、保护的重要场所,电气安装工程质量的好坏直接影响整个工程的质量,对供电可靠性有着重要作用。通过对1O kV配电室安装施工过程进行分析,建立严格的管理措施,按照各个环节的控制措施严格进行施工,对保证配电室设备安全运行和可靠供电具有重要意义。
参考文献:
[1] 李天友.配电技术EM3.北京:中国电力出版社,2008.
[2] 李道安,肖 杰.变配电室施工中关键工序控制[J].青岛理工大学学报,2007,28(5):114—116.
[3] 李丽丽.新建配电室关键的几个技术问题[J].化工安全与环境,2OlO(3):7—8.
注:文章内所有公式及图表请以PDF形式查看。
关键词:配电室;安装施工;控制措施
Abstract:10kV distribution chamber is composed of distribution transformer, high voltage switchgear, low voltage switch cabinet, busbar and its auxiliary equipment, according to a certain mode of connection is combined and arranged into power facility, its role is to transform and distribution of electric voltage and direct the nearest to the low-voltage power supply, it is the city of supply and distribution system in of the importance constitute part. Power distribution room to install the construction process is relatively complex, high quality requirements of electrical equipment installation. The article analyzes the 1O kV distribution room installation construction process on several important aspects, and puts forward the construction process should pay attention to the problems and corresponding measures, in order to ensure engineering quality.
Key words:Electricity distribution room;Installation and construction;Control measures
中图分类号:TM641 文献标识码:A文章编号:2095-2104(2012)
前言:
随着广东地区全面建设小康社会步伐的加快和城市化建设的快速发展,中小城镇居民住宅小区的建设如雨后春笋般的发展起来,中小城镇居民小区的出现,说明了改革开放以来,人们生活得到了极大改善,同时,也为电力企业实现可持续发展,营造了一个大好的发展机遇。
1 安装施工过程及要求
10 kV配电室安装施工主要包括土建施工、基础型钢的施工、高低压开关柜的安装、桥架和母线支架施工、母线安装以及电缆进出线的施工。以下表一详细分析安装施工过程的具体要求。
2 施工过程中的控制措施
通过以上分析可以看出,配电室内部施工工序较多,内部因素彼此之间也形成了互相制约的条件。为确保配电室工程质量,首先应建立配电室安装施工中的管理措施,对设备安装中各工序严格按照GB 50303—2002《建筑电气工程施工质量验收规范》的要求进行施工。配电室的安装施工质量控制分为准备、施工、调试和送电4个关键环节,在各个环节建立有效的管理措施,并严格执行,按照质量标准检查、监督。
2.1 准备环节控制措施
供电部门对配电室一次原理图进行审核并确认,设计部门对设备中标厂家提供的高低压配电系统二次原理图审核确认。电气设备到场后,监理部门验收资料是否齐全,设备资料和厂家提供的配件及钥匙等设专人管理,防止重要资料及钥匙丢失。
设备安装前编写施工组织设计和设备施工方案,审批后方可进行设备安装施工。施工中严格按照图纸及厂家提供的基础图进行基础、接地装置及管线的预留预埋。预留预埋时,电气施工人员要与土建施工密切配合,确保槽钢基础的水平度、平行度
符合规范要求。槽钢基础施工完毕后要使用水准仪进行实测验收,当水平度和平行度不满足规范要求時,要进一步进行调整,直至符合规范要求为止。
2.2 施工环节控制措施
安装施工阶段主要包括高低压开关柜的就位、高低压开关柜内铜排穿引安装及二次线的穿引敷设、高低压桥架的安装、母线的安装、风管的安装,设备安装中各工序要严格按照标准要求进行施工。对于常见的设备质量问题(如零排缺件、母排的固定支架数量不够、开关的复位按钮不能复位、个别元器件缺失、设备外壳接地线线径过小或未直接与接地体连接等)应逐一排查、验收,整改不符合要求项。
设备安装阶段工序按先后依次为:高低压设备的就位,高低压开关柜铜排穿引及二次线的敷设,封闭母线的安装、风管的安装、桥架的安装。这样安排可尽可能减少各工序之间的破坏及污染,保证施工进度。就位安装按照从里到外的顺序依次进行,以便于后续设备的运输和安装。质量控制措施主要从以下几个方面进行控制:做好配电室桥架、母线、风管、设备的综合平面图,确定好位置、标高。如果它
们之间的标高或者位置出现矛盾,原则上应优先考虑设备的位置和标高,再考虑母线的位置和标高,然后是风管的位置和标高,最后是桥架的位置和标高。
2.3 调试环节控制措施
设备调试及送电方案编制审批完毕,设备调试所需要的仪器准备齐全,配电室电气设备试验全部合格,如变压器、断路器、电缆的耐压试验;变压器各绕组的直流电阻值、变比试验;断路器失压脱扣和重合闸试验;直流屏的试验;计量TA 和TV 的试验;低压电器设备的试验,低压开关柜与低压开关柜之间联络用低压断路器接三相电模拟试验等。
2.4 送电环节控制措施
送电前应对下列工作内容进行逐条落实:计量表的安装;进线保护的整定;各种合同协议的签订;运行规程的编制;运行人员的取证、培训;配电室内安全用具的配备(如绝缘板、灭火器、绝缘手套、绝缘鞋、验电器、标志牌、规章制度牌、接地线、应急灯等);直流屏的充电,便于高低压开关柜的操作;悬挂高低压二次接线图等。
送电时,送电顺序必须严格按照送电方案执行,操作过程必须符合规范要求。操作人员必须持证上岗并充分了解配电室内的一二次配电原理。
3 结束语
10 kV配电室是电能控制、保护的重要场所,电气安装工程质量的好坏直接影响整个工程的质量,对供电可靠性有着重要作用。通过对1O kV配电室安装施工过程进行分析,建立严格的管理措施,按照各个环节的控制措施严格进行施工,对保证配电室设备安全运行和可靠供电具有重要意义。