湛江港一区南一期工程是全国重点建设工程之一,系由六个万吨级深水泊位组成的突堤式码头。该工程由第四航务工程勘察设计院设计,第四航务工程局第三工程公司施工。水工建筑由81年开工至84年底基本建成,其中两个泊位已交工投产。陆上土建工程的1~5号大仓库(其中1~4号大仓库的建筑面积均为1万米~2)于83年开工,84年底2号和4号仓库已建成交付使用,其余主体已完工。散粮圆筒仓系统土建工程83年开始打桩,其滑模施工于84年4月1日开
Zhanjiang Port Area South Phase I Project is one of the key construction projects in the country and is a jetty pier consisting of six 10,000-ton deep water berths. This project is designed by the fourth flight engineering survey and design institute and the third engineering company of the fourth navigation engineering bureau. Hydraulic construction started from 81 to the end of 84 basically completed, of which two berths have been put into production. On land civil engineering 1-5 large warehouses (of which 1 to 4 large warehouses have a building area of 10,000 meters ~ 2) started construction in 83, and the warehouses No. 2 and No. 4 at the end of 84 have been completed and delivered for use. The remaining subjects Completed. Bulk grain silo system civil engineering started piling 83 years, the sliding mode construction on April 1, 1984 to open