风电项目开发环节需要较长时间,从获取场址到工程建设准备就绪,这一过程需时3年~4年。工程建设准备就绪是指:项目建设和运行所需的全部许可和环保审批均已获得,对足够的风能资源数据所进行的收集和分析已经完成,允许该项目接入现有电网的并网协议已得到全面履行,一切必要的输电安排均已确定,且为全部电力购销而制定的电力购买协议或其他电力承购合约已签署完毕。至此,风电机组供应及电场配套设施的采购和施工(EPC)协议方可订立,可
Wind power project development takes a long time, from obtaining the site to construction ready, the process takes 3 years to 4 years. The construction is ready means that all the permits and environmental approvals needed for the construction and operation of the project have been obtained. The collection and analysis of sufficient wind energy resource data has been completed and the project is allowed to access the grid interconnection agreement of the existing power grid Has been fully implemented and all necessary transmission arrangements have been finalized and the power purchase agreement or other power purchase contract established for the full purchase and sale of electricity has been completed. At this point, the purchase and construction (EPC) agreement of wind turbine supply and electric field facilities can be concluded, but