论文部分内容阅读
和Base Date“基准日期”一样,建设工程合同中Commencement Date “开工日期”也是一个对当事人权利义务关系会产生重要影响的时间节点.rn例1——“Commencement Date” means the date notified under Sub-Clause 8.1 [Commencement of Works] (1.1.3.2). The Engineer shall give the Contractor not less than 7 days’ notice of the Commencement Date. Unless otherwise stated in the Particular Conditions, the Commencement Date shall be within 42 days after the Contractor receives the Letter of Acceptance. … (8.1). (Contract for Construction, FIDIC, 1999)