2013年12月10日,国网湖南电力检修公司完成了500千伏黑沙线线路直流融冰装置升流试验。这是湖南主电网移动式直流融冰装置首次在超高压线路上进行升流试验。据了解,为检验融冰装置的实际融冰能力和改进融冰技术方案,国网湖南电力检修公司在每年融冰警戒期到来前,都会安排一次线路模拟融冰试验,但以前仅限于在试验设备上进行模拟,并未真
On December 10, 2013, the State Grid Hunan Electricity Maintenance Company completed the upflow test of the DC ice melting plant on the 500 kV Heisha line. This is the first time in Hunan’s main grid mobile DC ice melting device in the UHV line up-flow test. It is understood that in order to test the actual ice melting ice melting capacity and improve the ice melting technology program, the State Grid Hunan Power Maintenance Company ice melting alert every year before the arrival of a line will be arranged to simulate ice melting test, but previously limited to the test Equipment simulation, not really