针对调度领域研究中有交货期限要求的Job-Shop工件装配调度算法,提出了一种逆序初排调度算法及调整算法,并给出了目标函数.通过分析与实例验证,所提出的算法在解决企业的实际生产调度问题时,取得了比较满意的效果.
Aiming at the Job-Shop assembly scheduling algorithm with delivery deadline in the research of dispatching field, a reverse scheduling algorithm and its adjustment algorithm are proposed, and the objective function is given. Through the analysis and example verification, the proposed algorithm has achieved satisfactory results when solving the actual production scheduling problem in enterprises.