1.工程概况本工程筒仓直径12.44m,标高60.5m,壁厚为300mm、220mm,共12座连体仓,标高—4.400-60.050m,采用滑膜施工,8.00m处星仓设底板,50.50m为屋面板。2.筒仓滑模施工2.1施工前准备滑膜施工是一种随浇筑砼,随绑扎钢筋,随滑升模板,连续交叉作业,不间断的一种快速施工好先进的施工工艺,因此必须做好充分的各项准备工作。本工程12个连体筒仓,配置主要液压滑升设备有:YHJ-56型液压控制台和YHJ-36型液压控制台各两台(可控制480个千斤顶),配置GYD-35型液压千斤顶400只(其中备用64只)油管及针阀等均与
1. Project Overview This project has a silo diameter of 12.44m, elevation of 60.5m, wall thickness of 300mm and 220mm, a total of 12 conjoined warehouses, elevation of 4.400-60.050m, construction of sliding membranes, and 8.00m at the star warehouse floor. 50.50m is a roof panel. 2. Silo sliding mode construction 2.1 Preparation before construction Synovial membrane construction is a kind of construction process with the pouring of concrete, with the tying steel, with the sliding template, continuous cross-operation, an uninterrupted construction of a rapid and advanced construction technology, it must be done Good preparations. The 12 Siamese Silos of this project are equipped with hydraulic sliding equipment: YHJ-56 hydraulic control console and YHJ-36 hydraulic control console with two each (480 jacks can be controlled), and GYD-35 hydraulic jacks are configured. 400 (of which 64 are spare) tubing and needle valves are all