三峡永久船闸是三峡水利枢纽的主体工程之一。武警水电部队官兵在一千多个日夜的艰苦鏖战中,科学求实攻克世界级难题,顽强拼搏确保质量和工期,用智慧和血汗谱写了当代军人建设祖国的豪迈篇章。一堵墙,一道世界级难题,一个世界奇迹1995年底,武警水电部队以提前8天的优异成绩,胜利完成永久船闸一期开挖任务后,进入二期施工一年,就遇到了“拦路虎”。根据工程设计,须开挖一堵68.5米深的直立墙,上下误差不能超过20厘米,墙体不能产生一丝一毫的裂纹或松动。这不是在模具里的铸造,也不是
The Three Gorges Permanent Ship Lock is one of the main works of the Three Gorges Project. In more than a thousand days and nights of arduous battles, the armed police power and water officers and men conducted scientific and pragmatic attempts to overcome world-class problems, worked hard to ensure quality and timeliness, and prepared the heroic chapter in the construction of the motherland by contemporary military personnel with wisdom and bloodshed. A wall, a world-class problems, a world of miracles By the end of 1995, Armed Police Corps to 8 days in advance of the outstanding achievements of the permanent completion of a permanent ship lock excavation task, entered the second phase of construction a year, encountered a “stumbling block ”. According to the design of the project, an upright wall with a depth of 68.5 meters shall be excavated. The upper and lower error shall not exceed 20 cm. The wall shall not produce slightest cracks or looseness. This is not casting in the mold, nor is it