某住宅小区5号楼工程,地下2层,地上3l层,总建筑面积1.72万m2,建筑总高度98.65m。拟采用一台TC5613塔式起重机作为吊装运输工具。根据施工总体部署,该工程在地下工程施工前已完成塔式起重机基础承台施工,塔式起重机在完成±0.000以下工程后安装。塔式起重机基础采用“钻孔灌注桩+高桩承台”形式。塔式起重机平面布置如图1所示。该项目完成±0.000以下结构后。建设单位根据市场反馈,对5号楼原户型做了调整,导致5号楼建筑平面轮廓变化。见图2
A residential district Building 5 project, 2 underground, 3l above ground, with a total construction area of 17200 m2, the total construction height of 98.65m. It intends to use a TC5613 tower crane as a lifting transport. According to the overall deployment of the construction, the project has completed the construction of tower crane foundation cap before the construction of underground works. The tower crane is installed after the completion of the project of ± 0.000. Tower crane based on “bored pile + high pile cap ” form. Tower crane plane layout shown in Figure 1. After the project is completed ± 0.000 the following structure. According to market feedback, the construction unit made adjustments to the original apartment building No. 5, resulting in the change of floor plan of No. 5 building. See Figure 2