湖南衡阳白地市钢铁厂1996年底50m~3高炉大修,历时88天。1997年三月末复风,第一个月产铁即达2580t,创历史最好水平。这次修炉工作量最大,资金最紧,仅对少数关键项目进行了改造,冲渣水循环使用上行车就是其中之一。水渣系统改造全部面积374m~2,露天跨L=10.5m 5t双梁抓斗吊行车一名,水渣池h=-3.2m V=420m~3 可容纳3~5天水渣;布袋除尘系统瓦斯灰利用原地稍加改进砌成,此外就是水沟与集水器钢结构件等耗资不到30万元。这样取代了原来很小的渣池与旋转吊,
Hengyang, Hunan Baodi Steel Plant by the end of 1996 50m ~ 3 blast furnace overhaul, which lasted 88 days. At the end of March 1997, there was a return to the wind. The first monthly iron production reached 2580 tons, the best record in history. This repair furnace maximum workload, funding the most tight, only a few key projects have been transformed, red slag on the water cycle is one of them. A total of 374m ~ 2 for reconstructing the water slag system, one for a double girder grab crane with an open span of L = 10.5m and a slag pool h = -3.2m V = 420m ~ 3 for 3 ~ 5 days. Gas ash use a little improvement in place of a little brick, in addition to the ditch and catchment steel structure, etc. cost less than 30 million. This replaced the original small slag pool and rotary crane,