主厂房开始屋架吊装10月17日星期四天气晴主厂房屋架今天开始吊装,比原计划推迟了整整一个月。今天,主厂房现场气氛非常热烈,道路两旁十多面彩旗在微风中飘扬。汽车吊已稳稳坐落于主厂房中间,32m高的吊杆直插云霄,新增设的鹅头吊杆十分引人注目。公司总工程师、技术科、设备科和本项目部的钱经理、赵工程师以及业主方、监理方领
The main plant began to hoist the roof Thursday, October 17 The weather main factory roof truss began to hoist today, than the original plan postponed for a whole month. Today, the main factory atmosphere is very warm, more than a dozen of flags on both sides of the road fluttering in the breeze. Car crane has been firmly located in the middle of the main plant, 32m high boom straight into the sky, the new addition of goose head boom is very compelling. Company chief engineer, technical department, equipment department and the project manager money manager, Zhao engineer and the owner side, supervision side collar