湖北省利川市自来水公司已有40多年历史,资产总额1400万元,拥有DN75mm以上管网45公里。 公司二水厂项目于1998年立项,2001年12月湖北省计委批复了二水厂变更方案可行性研究报告,2002年2月批准初步设计方案。该项目建设规模为6万吨/日,分两期建设,第一期为3万吨/日,工期为3年,建设主要内容为净水厂、水库、输水管道,总投资
Lichuan City, Hubei Province water company has more than 40 years of history, with a total assets of 14 million yuan, with pipe network DN75mm above 45 km. The second waterworks project of the Company was approved in 1998. In December 2001, the Planning Commission of Hubei Province approved the feasibility study report of the second waterworks modification plan and approved the preliminary design scheme in February 2002. The project has a construction scale of 60,000 tons / day and is constructed in two phases. The first phase is 30,000 tons per day and the construction period is 3 years. The main contents of the project are water purification plants, reservoirs and water pipelines, and the total investment