1 1958~1970年:从高炉新建到投产的艰难历程 1958年6月3日,国务院批复了酒钢的设计任务书,8月1日酒泉钢铁公司宣布正式成立。1号高炉(1513m~3)于1958年9月15日破土动工,1960年底因国家经济困难被迫下马停建。当时,酒钢只有少部分职工留守,与他们日夜相伴的是矗立在戈壁滩上的高炉炉壳。 经过3年的恢复调整,国家经济建设步入正常的发展轨道,1964年全国掀起三线建设的
1 1958-1970: A difficult journey from blast furnace construction to commissioning On June 3, 1958, the State Council approved the design task of Jiuquan Steel and officially announced the establishment of Jiuquan Iron and Steel Company on August 1. The blast furnace No. 1 (1513m ~ 3) broke ground on September 15, 1958, and was forced to suspend construction at the end of 1960 due to the country’s economic difficulties. At that time, only a small part of Jiuquan staff left behind, accompanied by them day and night is standing on the Gobi desert blast furnace shell. After three years of restoration and adjustment, the country’s economy has entered a normal track of development. In 1964, the construction of the third-line nationwide