1.施工前,应根据设计和本规程要求以及相关的技术标准编制针对工程项目的节能保温专项施工方案,并应对施工人员进行技术交底和专业技术培训。2.岩棉板外保温系统用于节能保温工程的施工应按照经审查合格的施工图设计文件和经审批通过的用于工程项目的节能保温专项施工方案进行。3.岩棉板外保温系统的生产企业应有专业人员在施工过程中进行现场指导,并配合施工单位和现场监理做好施工质量控制工作。
1. Before construction, should be based on the design and the requirements of this code and the relevant technical standards for the preparation of energy-saving projects for the construction of special insulation and construction workers should pay technical and technical training and professional training. 2. Rock wool insulation system used for energy-saving insulation construction should be in accordance with the review of qualified construction drawings design documents and approved by the project for the energy-saving insulation special construction program. 3. Rock wool board insulation system manufacturers should have professionals in the construction process of on-site guidance, and with the construction unit and on-site supervision of construction quality control.