江西省南昌县南新大口湖电排站建于20世纪60年代初期,是江西省南昌县发展电排事业的第一批试点电排站。该站整体布置不同于一般的电排站形式:在堤身上有两座穿堤闸,一座引水闸,一座出水闸,引水闸底板与机房底板高程基本一致。机房水箱布置在堤边内侧,中轴线与堤线平行。该站是排灌两用形式,是南新乡骨干电排站。装机4台,共720kW,配36寸轴流水泵。 1999年汛期高水位时,在堤内坡
Nanchang Dachang Lake, Nanchang County, Jiangxi Province was built in the early 1960s and was the first batch of experimental drainage stations in Nanchang County, Jiangxi Province. The overall layout of the station is different from the general form of the power plant: There are two dike barriers on the dike body, a floodgate, a floodgate, floodgate floor and the engine room floor is basically the same elevation. The engine room water tank is arranged inside the embankment side, the central axis and embankment line parallel. The station is a dual form of irrigation and drainage, is the backbone of South Xinxiang Power Plant. Installed 4, a total of 720kW, with 36-inch axial flow pump. Flood season in 1999, when the dike slope