论文部分内容阅读
《临钢科技》1982年第2期发表了阎中勇署名的《关于改进24m~2烧结机尾废气净化工艺的初步设想》一文,现摘其要点转载如下。临汾钢铁公司(以下简称“临钢”)在使用24m~2烧结机生产烧结矿中,对机尾废气采取的净化工艺为:单辊吸尘点、热矿筛吸尘点、振冷机头吸尘点、大烟道及返矿吸尘点→废气总管→并联两台 CLP/B 型旋风除尘器→Y4-73-11No12D 型锅炉引风机→废气排放管。据1981年3~4月间长沙矿山设计院对1~#烧结机尾废气净化含尘情况进行的测定
“Lin Steel Science and Technology,” 1982 the second issue of Yan Zhongyong signed “on the improvement of 24m ~ 2 sintering tail exhaust gas purification technology,” a text, now pick the main points reproduced below. Linfen Iron and Steel Company (hereinafter referred to as “Lin Gang”) in the use of sinter 24m ~ 2 sinter production, tail exhaust gas purification process to take: single roller vacuum cleaning point, hot mineral vacuum cleaning points, vibrating head Vacuuming point, large flue and dust recovery point → exhaust manifold → two CLP / B cyclone dust collector → Y4-73-11No12D boiler draft fan → exhaust pipe. According to 1981 March to April, Changsha Institute of Mining Design 1 ~ # sintering tail exhaust gas purification dust conditions were measured