自1896年修建了海河防潮闸以来,每逢干旱年份,上游淡水来源枯竭,海水不断侵入海河,造成淡水污染,影响工农业用水,迫使每年在海河干流临时打坝蓄水,到了汛期又仑促拆坝,以利泄洪。年复一年不但浪费了大量的人力和资金,而且还造成海河干流的淤积。为此天津市政府决定距入海口30多公里处的东泥沽村东修建海河二道闸。工程于1984年8月动工,1985年12月竣工。建设者们冒着严寒酷暑奋战了500个日日夜夜,建成了一座能泄1200流量的枢型工程(包括船闸和公路桥等)。水闸不但起到保护水质、汛期泄洪的作用,而且使海河干流航道得到充分开发,并沟通了南北交通,为天津市新工业区的开发建设、发展旅游事业创造了有利条件。
Since the construction of the Haihe Moisture Barrier in 1896, freshwater sources in the upper reaches have been depleted in dry years and seawater has continuously invaded the Haihe River, causing freshwater pollution and affecting industrial and agricultural water use, forcing a temporary dam water storage in the mainstream of the Haihe River every year. Demolition dam to facilitate flood discharge. Year after year not only wasted a lot of manpower and capital, but also caused the deposition of Haihe River. To this end, the Tianjin Municipal Government decided to build the Haihe Second Barrier at Donggugu Village East, more than 30 kilometers away from the sea entrance. Construction started in August 1984, completed in December 1985. The builders braved the cold and heat to fight for 500 days and nights, built a 1,200 traffic capacity of the hinge project (including shiplocks and road bridges, etc.). The sluice not only serves to protect the water quality and flood discharge during the flood season, but also fully exploits the channel of the mainstream of the Haihe River and communicates with the north and south traffic. This has created favorable conditions for the development and construction of the new industrial zone in Tianjin and the development of tourism.