摘要:本工程为杭州七格污水处理厂一期5万吨/日设备购置及安装工程。本次主要在原有土建预留位置进行设备安装,由于土建部分已建,并与原一期共用,导致部分构建筑物需要停水进行施工,同时厂内其他系统照常生产。本次限水切改的主要目的在于在不停产,少减产的条件下,确保施工人员安全,保证施工质量,打通5万吨系统与原一期系统的水、电、气、泥路,保证杭州地区减排量。
关键词:设备安装;节能环保;污水处理
Abstract: the engineering for hangzhou seven case a sewage treatment plant of 50000 tons/day equipment purchase and installation. The main reserve position in the original civil equipment installation, because the civil part already built, and a period with the original share, leading some compose the buildings need to stop water for construction, at the same time, other system in factory production as usual. The limited water cut is the main purpose of the change in don't stop production, cut less, under the condition of construction personnel to ensure safety, ensure the quality of construction through 50000 tons and the original system of system of water, electricity, gas, entailed, guarantee the hangzhou area reduction.
Keywords: equipment installation; Energy conservation and environmental protection; Sewage treatment
中圖分类号:TE08文献标识码:A 文章编号:
一、 停水施工情况:
本次限水,主要对厂区余杭进水系统实行切换并减量运行,保证5万吨工程施工顺利实施。主要施工点位为进水计量井、初沉池进水渠、生物池出水渠、外回流污泥渠、二沉池进出水管及排泥管以及空气管道对接、分变电站施工等。
1、进水计量井:
该点位施工过程:
第一,关闭7#、8#细格栅前两台渠道闸(A)及7#、6#之间的连通闸(B),防止旋流沉砂池的水回灌,并切断与其他系统的联通。
第二,拆除DN900闸阀侧面DN200闸阀,拆除后利用该管进行放空管内余水,通过余杭计量井集水坑中DN200排水管排至北侧三污计量井中,统一外调。
第三,余水排净后,拆除现状管道及闸阀,用汽车吊将拆除管件吊至计量井外。
第四,将已做好防腐的新管道及新采购的闸阀吊至井内,按图进行安装,流量计预计无法到场,因此将流量计及伸缩节位置空出。
第五,关闭安装好的闸阀,恢复通水。
需要运营方配合的工作:
1) 余杭计量井停水后,图示三污系统需保持正常运行水位(栅前水深1.2米,栅后水深1米),防止污水通过溢流孔流至余杭系统,影响施工。
2) 三污系统计量井内排水泵需正常运行,配合余杭系统排水,防止污水将三污井内流量计及电动阀淹没。
2、初沉池进水渠道
初沉池来水示意图
初沉池进水渠道示意图
该点位施工过程:
第一,停止余杭系统进水,关闭4#沉砂池进出水及出水联通闸门,打开7#初沉池全部进水闸门,继续进水。
第二,待进水渠液面降至低水位时,关闭进水闸门,利用水泵将进水渠内污水排至7#初沉池内,继续降低液位;同时,利用高压水枪对8#初沉池一侧渠壁进行冲洗。
第三,安装三台进水闸门,并进行二次浇注;同时,拆除8#初沉池超越渠封堵,并清理。
3、生物池出水渠道
第一,待初沉池降至较低低水位时,关闭7#生反池出水调节堰。
第二,对回流渠道进行降水、清理;
第三,拆除8#生反池两处出水堰封堵(5.25m×1.25m×0.25m),并安装渠道闸门及出水调节堰门。
第四,对渠道闸及出水调节堰进行二次浇注,养护。
4、二沉池拆除封堵
该施工点位特点:8#二沉池与5、6、7#二沉池共用一座配水井及外回流渠。在拆除封堵前,需要将配水井及外回流污泥渠内污泥全部置换干净,方可保证施工安全。
由于三处封堵所在位置较深(3-4米),封堵厚度较大(约40公分),污泥沉淀时间较长(建厂至今)且不易冲洗置换(均处在管网末梢),因此作为本次施工的安全重点部位。
利用厂里电气改造Ⅰ段停电时进行。
第一,将5#、6#、7#二沉池排泥阀升至液位以上,停止排泥。
第二,利用厂里回流污泥泵拉低管道内泥位。
第三,安排施工作业人员进行拆堵及清理。
需要运营方配合的工作:
1) 提升5~7#二沉池排泥阀至液位以上,停止排泥;
2) 利用回流泵拉低管道内泥位,防止施工时污泥外泄。
5、空气管路对接
该工作点施工需要与电气施工相结合,安排在电气施工时进行。待电气施工至Ⅱ段时,需要停电接线,届时鼓风机需要停机,利用该段时间对预留盲板进行拆除,安装上手动蝶阀,并与入户新空气管道完成对接工作。
6、电气施工专篇
本工程低压用设备主要集中在初沉池及生物池,原1#变电站低压系统利用原备用回路引出三路直供初沉池及生物池上的动力箱。均选用YJV22-13*70+1*35电缆,三条出线回路其中二条从低压供电系统Ⅰ段母排引出,另一条从Ⅱ段母排引出。
Ⅰ段母排二路出线施工时,必须将Ⅰ段母排所带用电设备切断电源,同时1#变压器停运,系统母联开关仍处切开状态,操作时间约4小时,(停电时间),Ⅱ段母排一路出线施工时情况同上,操作时间约2~3小时。
计划3月19日、20日二天时间将三根从1#变引出的电缆敷设完,同时完成电缆头制安工作、电缆绝缘检测工作,21日上午10点1#变Ⅰ段母排停电。(完成从Ⅰ段母排引出回路的压线工作、及更换主开关、CT)4小时内完成并可恢复供电,21日下午2点1#变Ⅱ段母排停电。(完成从Ⅱ段母排引出回路的压线工作、及更换主开关、CT)2~3小时恢复供电。
二、 总结
本次限水施工组织有效、配合默契、在相关单位的配合和施工预案的保障下,提前三天完成了预期计划的施工内容(对二次浇注的混凝土添加早强剂,缩短养护时间)。通过本次施工,使我方施工水平、组织水平和协调能力得到了提高,是不可多得的一次锻炼。
注:文章内所有公式及图表请用PDF形式查看。
关键词:设备安装;节能环保;污水处理
Abstract: the engineering for hangzhou seven case a sewage treatment plant of 50000 tons/day equipment purchase and installation. The main reserve position in the original civil equipment installation, because the civil part already built, and a period with the original share, leading some compose the buildings need to stop water for construction, at the same time, other system in factory production as usual. The limited water cut is the main purpose of the change in don't stop production, cut less, under the condition of construction personnel to ensure safety, ensure the quality of construction through 50000 tons and the original system of system of water, electricity, gas, entailed, guarantee the hangzhou area reduction.
Keywords: equipment installation; Energy conservation and environmental protection; Sewage treatment
中圖分类号:TE08文献标识码:A 文章编号:
一、 停水施工情况:
本次限水,主要对厂区余杭进水系统实行切换并减量运行,保证5万吨工程施工顺利实施。主要施工点位为进水计量井、初沉池进水渠、生物池出水渠、外回流污泥渠、二沉池进出水管及排泥管以及空气管道对接、分变电站施工等。
1、进水计量井:
该点位施工过程:
第一,关闭7#、8#细格栅前两台渠道闸(A)及7#、6#之间的连通闸(B),防止旋流沉砂池的水回灌,并切断与其他系统的联通。
第二,拆除DN900闸阀侧面DN200闸阀,拆除后利用该管进行放空管内余水,通过余杭计量井集水坑中DN200排水管排至北侧三污计量井中,统一外调。
第三,余水排净后,拆除现状管道及闸阀,用汽车吊将拆除管件吊至计量井外。
第四,将已做好防腐的新管道及新采购的闸阀吊至井内,按图进行安装,流量计预计无法到场,因此将流量计及伸缩节位置空出。
第五,关闭安装好的闸阀,恢复通水。
需要运营方配合的工作:
1) 余杭计量井停水后,图示三污系统需保持正常运行水位(栅前水深1.2米,栅后水深1米),防止污水通过溢流孔流至余杭系统,影响施工。
2) 三污系统计量井内排水泵需正常运行,配合余杭系统排水,防止污水将三污井内流量计及电动阀淹没。
2、初沉池进水渠道
初沉池来水示意图
初沉池进水渠道示意图
该点位施工过程:
第一,停止余杭系统进水,关闭4#沉砂池进出水及出水联通闸门,打开7#初沉池全部进水闸门,继续进水。
第二,待进水渠液面降至低水位时,关闭进水闸门,利用水泵将进水渠内污水排至7#初沉池内,继续降低液位;同时,利用高压水枪对8#初沉池一侧渠壁进行冲洗。
第三,安装三台进水闸门,并进行二次浇注;同时,拆除8#初沉池超越渠封堵,并清理。
3、生物池出水渠道
第一,待初沉池降至较低低水位时,关闭7#生反池出水调节堰。
第二,对回流渠道进行降水、清理;
第三,拆除8#生反池两处出水堰封堵(5.25m×1.25m×0.25m),并安装渠道闸门及出水调节堰门。
第四,对渠道闸及出水调节堰进行二次浇注,养护。
4、二沉池拆除封堵
该施工点位特点:8#二沉池与5、6、7#二沉池共用一座配水井及外回流渠。在拆除封堵前,需要将配水井及外回流污泥渠内污泥全部置换干净,方可保证施工安全。
由于三处封堵所在位置较深(3-4米),封堵厚度较大(约40公分),污泥沉淀时间较长(建厂至今)且不易冲洗置换(均处在管网末梢),因此作为本次施工的安全重点部位。
利用厂里电气改造Ⅰ段停电时进行。
第一,将5#、6#、7#二沉池排泥阀升至液位以上,停止排泥。
第二,利用厂里回流污泥泵拉低管道内泥位。
第三,安排施工作业人员进行拆堵及清理。
需要运营方配合的工作:
1) 提升5~7#二沉池排泥阀至液位以上,停止排泥;
2) 利用回流泵拉低管道内泥位,防止施工时污泥外泄。
5、空气管路对接
该工作点施工需要与电气施工相结合,安排在电气施工时进行。待电气施工至Ⅱ段时,需要停电接线,届时鼓风机需要停机,利用该段时间对预留盲板进行拆除,安装上手动蝶阀,并与入户新空气管道完成对接工作。
6、电气施工专篇
本工程低压用设备主要集中在初沉池及生物池,原1#变电站低压系统利用原备用回路引出三路直供初沉池及生物池上的动力箱。均选用YJV22-13*70+1*35电缆,三条出线回路其中二条从低压供电系统Ⅰ段母排引出,另一条从Ⅱ段母排引出。
Ⅰ段母排二路出线施工时,必须将Ⅰ段母排所带用电设备切断电源,同时1#变压器停运,系统母联开关仍处切开状态,操作时间约4小时,(停电时间),Ⅱ段母排一路出线施工时情况同上,操作时间约2~3小时。
计划3月19日、20日二天时间将三根从1#变引出的电缆敷设完,同时完成电缆头制安工作、电缆绝缘检测工作,21日上午10点1#变Ⅰ段母排停电。(完成从Ⅰ段母排引出回路的压线工作、及更换主开关、CT)4小时内完成并可恢复供电,21日下午2点1#变Ⅱ段母排停电。(完成从Ⅱ段母排引出回路的压线工作、及更换主开关、CT)2~3小时恢复供电。
二、 总结
本次限水施工组织有效、配合默契、在相关单位的配合和施工预案的保障下,提前三天完成了预期计划的施工内容(对二次浇注的混凝土添加早强剂,缩短养护时间)。通过本次施工,使我方施工水平、组织水平和协调能力得到了提高,是不可多得的一次锻炼。