我单位施工的一幢54m×24m 框架结构三层两跨工业厂房,在三层柱子完成安装屋面梁模时发现,三层边柱少配钢筋30%。事故原因是误将二层柱截面用于三层,柱子施工中又未能及时发现。处理方案:考虑到如加固柱子,工程量太大,成本较高。后通过框架结构计算,将屋面梁设计高度800mm 改为900mm,屋面梁线刚度加大,角弯矩分配系数提高,柱角弯矩分配系数相对减小,达到了减小柱子弯矩满足承载力要求的目的。
I unit construction of a 54m × 24m three-story two-story industrial structure of the three-story two-span cross-pillar installation of the roof beam mode found that the three sides less than 30% of the side columns. The accident was mistakenly used for the three-story two-story column, column construction and failed to find in time. Treatment options: Taking into account, such as strengthening the column, the project is too large, the cost is higher. After the calculation of the frame structure, the design height of the roof beam is changed to 800mm, the rigidity of the roof beam is increased, the distribution coefficient of angular bending moment is increased, the distribution coefficient of moment of column angle is relatively reduced, and the reduction of the column moment satisfies the bearing capacity The purpose of the request.