自2012年12月新增厌氧项目竣工投运后,公司动力车间全力以赴投入到调试工作中,车间成立了以主任为组长,工艺、机修、电仪技术骨干为成员的调试小组,制定了专门调试方案,增加了专项调试记录。该车间根据新厌氧技术规程和以往厌氧运行经验,对进水挥发酸、温度等指标严格控制,逐步加大进水量,由初期的20m3·h-1,增加到现在的220m3·h-1;厌氧污泥
Since the project of adding anaerobic project was completed and put into operation in December 2012, the Company’s power plant devoted all its efforts to the commissioning work. The workshop set up a commissioning team with the director as its leader and the technical backbone of technology, mechanics and electrics as its members. Developed a special debugging program, an increase of special commissioning records. The workshop under the new anaerobic technical regulations and previous anaerobic operation experience, the water volatile acid, temperature and other indicators of strict control, and gradually increase the influent, from the initial 20m3 · h-1, to the current 220m3 · h- 1; anaerobic sludge