5月17日,合肥院设计的山东肥城米山日产4000吨熟料新型干法水泥生产线顺利竣工。该生产线自2011年3月30日破土动工,至竣工点火历时13个月。建设期间,合肥院与水泥厂通力协作,克服了施工场地狭小、老线分期拆除及与新征场地有机衔接等困难,多次及时调整总图布局和专业设计方案,对生产线从整体布局、工艺流程、电缆走向、土建设计等方面做了整体优化。该项目除已竣工的日产4000吨熟料生产线外,还包括6兆瓦余热发电系
May 17, Hefei Institute of Design Feicheng, Shandong Nissan Nissan 4,000 tons of clinker dry process of cement production line successfully completed. The production line broke ground from March 30, 2011 to completion of the ignition lasted 13 months. During the construction period, Hefei Institute collaborated with cement factory to overcome difficulties such as narrow construction site, demolition of old lines and organic connection with new leveled grounds, timely adjustment of master plan layout and professional design plan in many occasions, Process, cable direction, civil design, etc. to do the overall optimization. In addition to the completion of the project Nissan 4,000 tons of clinker production line, but also includes 6 MW of waste heat power generation system