随着基础工程的发展,桥梁高墩明显增多,而且施工场地狭窄,不适宜大型设备使用。通过翻模、爬模、滑模等工艺技术经济方面综合对比,选择采用交替提升模板进行薄壁高墩施工。交替提升模板由支架系统、模板和塔吊组成,相邻两墩共享一套模板和塔吊交替施工、易拆装,无需另设动力系统,成品质量好、施工安全性好,而且施工进度较快,特别易于山区狭窄地区施工操作。
With the development of basic engineering, the high pier of the bridge is obviously increased, and the construction site is narrow, which is not suitable for large-scale equipment. By turning the mold, climbing mode, sliding mode and other economic and technological aspects of the comprehensive comparison, choose to use alternating lifting template for the construction of thin-walled high pier. The alternating lifting template is composed of a support system, a template and a tower crane. Adjacent two piers share a set of formwork and crane alternately for construction, which is easy to disassemble and assemble without requiring a separate power system. The quality of the finished product is good, the construction safety is good, the construction progress is fast, Particularly easy to operate in the narrow area of mountainous areas.