株洲冶炼厂铜电解车间从一九七九年底开始拆除旧厂房到一九八零年六月十六日为止,历时6个月,年产万吨规模的铜电解新车间建成投产了,电铜质量合格率100%,一次投产成功,各项技术指标达到预订计划,比湖南省冶金局提出8月份建成投产的要求提前2个半日竣工,从根本上保证了八零年电铜生产计划的超额完成,从而为全厂实现年利润4300多万
The copper electrolysis plant in Zhuzhou Smelter started to demolish the old factory building from the end of 1979 to June 16, 1980 and took 6 months to complete the commissioning of a new copper electrolysis plant with an annual output of 10,000 tons. The copper Quality qualified rate of 100%, a successful operation, the technical indicators have reached the booking plan than the Hunan Provincial Metallurgical Bureau put forward the requirements of completed and put into operation in August completed two and a half days ahead of schedule, fundamentally guaranteed the excess of 80 plan for the production of copper Completed, thus achieving annual profit of more than 4300 million for the whole plant